The NC6 is ESB Networks' free microgeneration notification: the form that tells the grid operator a small solar system is connected at your home. Your installer submits it before the system is switched on, registered to your MPRN, and it costs you nothing. It is part of what lets your supplier pay you under the Clean Export Guarantee.
Solar Ireland files NC6s as a routine part of every domestic install, so here is exactly what the form is, who does what, and why it is one of the quieter but more important steps in going solar.
The NC6 is the standard notification form used to tell ESB Networks that a small generator - your solar PV system - has been connected at your property. Under the Microgeneration Support Scheme, domestic systems up to a set size can connect on an 'inform and fit' basis: your installer tells ESB Networks about the system before it is connected, rather than applying for a connection offer and waiting for it (esbnetworks.ie). It is registered against your MPRN, the 11-digit meter point number on your electricity bill.
It is free
ESB Networks does not charge for a domestic NC6 microgeneration notification. If anyone tells you there is a grid-connection fee for a standard home solar system, ask them to point to it - for a normal domestic install, there isn't one.
Your installer does. Submitting the NC6 is standard installer work and should be included in the job with nothing for you to fill in. It is also a useful quality marker: an installer who handles the NC6, sends SEAI the grant completion paperwork and coordinates the smart meter as a matter of course is one who does this properly. If a quote is silent on who files the NC6, ask.
You can submit the NC6 yourself, but ESB Networks recommends your installer or electrician completes it, because it asks technical questions about the inverter and its protection settings (esbnetworks.ie). It goes in before the system is connected: ESB Networks does not allow a microgenerator to be connected until it has received the notification. Applications cannot be backdated, and export counts from the date ESB Networks processes yours.
The NC6 Notification Form is published by ESB Networks on its micro-generation page. You can download it there or request a copy on 1800 372 757. ESB Networks takes it two ways:
Do not email it
ESB Networks says it no longer processes microgeneration applications sent by email. Use the online route or the post (esbnetworks.ie).
Your installer does this for you on a Solar Ireland job. If you want to know what goes on the form, or you are checking someone else's work, this is the order it runs in. Always use the current form from esbnetworks.ie, because ESB Networks revises it.
Check the MPRN twice
You cannot amend a submitted NC6: ESB Networks asks you to cancel it and send a corrected one, which restarts the clock. The MPRN and the type test certificate are the two details worth checking before it goes.
Nothing, for a domestic microgeneration connection. The value of solar is in the electricity you generate and the export you earn, not in connection fees - there are none to worry about for a standard home system.
They are both ESB Networks connection forms, used at different scales. The NC6 is the notification route for small microgeneration - the domestic and small-business systems most homeowners install. Larger generators that exceed the microgeneration thresholds move onto a full connection application process rather than a simple notification. For a typical Irish home, the NC6 is the form that applies.
| NC6 | Larger connections | |
|---|---|---|
| Used for | Domestic / small microgeneration | Generators above microgen limits |
| Process | Notify ESB Networks | Full connection application |
| Who files it | Your installer | Applicant / developer |
| Cost (domestic) | Free | Application and connection charges apply |
The NC7 is ESB Networks' application for mini-generation: inverter-connected generators up to 17 kVA single-phase or 50 kVA three-phase (esbnetworks.ie). Unlike the NC6 it carries an application fee, ESB Networks issues a connection offer that you accept before connecting, and the installer sends an installation confirmation certificate once the work is done.
| NC6 (micro-generation) | NC7 (mini-generation) | |
|---|---|---|
| Size | Up to 25 A single-phase (about 6 kVA) or 16 A per phase three-phase (about 11 kVA) | Up to 17 kVA single-phase or 50 kVA three-phase |
| Process | Inform and fit: notify before connecting | Apply, receive a connection offer, accept it |
| Fee | None | Application fee applies |
| Typical user | A home or small business | Larger homes, farms and businesses |
ESB Networks says it issues your Maximum Export Capacity within 20 working days of a complete, correct NC6, and longer if it has to go back to your installer for details (esbnetworks.ie). A good installer files it when the job is booked, so the NC6 does not hold up your installation. What the NC6 and your smart meter unlock is the export side: getting credited for surplus electricity you send back to the grid.
Yes. To earn Clean Export Guarantee (CEG) payments you need two things in place: a smart meter, so your export can be measured, and your system registered with ESB Networks via the NC6, so the grid knows there is a generator at your MPRN. With both sorted, your supplier pays you for exported units - roughly €410 to €480 a year on a 4 kWp system with no battery, depending on how much you use at home, and the first €400 a year of that income is tax-exempt. More in our Clean Export Guarantee guide and our smart meter guide.
Your MPRN (Meter Point Reference Number) is the unique 11-digit number that identifies your electricity connection. It is printed on your bill; see what is my MPRN and where to find it. The NC6 uses it to register your solar system against the correct connection, which is why an accurate MPRN is one of the details the installer confirms at survey.
Skipping the NC6 is not something a proper installer does. Without it, your system is not registered on the grid, which means you cannot be set up correctly for export payments and you are outside the microgeneration process the scheme is built on. It is free and standard, so there is no good reason to leave it undone - make sure your installer commits to filing it.
No. They are completely separate. Planning permission is about whether you are allowed to fit the panels - and for almost all houses rooftop solar is exempted development, so no permission is needed. The NC6 is about connecting the finished system to the grid. Our planning guide covers the permission side.
You need a smart meter to be paid for export, and ESB Networks is rolling them out nationally. Your installer coordinates the smart meter and the NC6 so the export side comes together after the system is live.
Yes. ESB Networks publishes the form on esbnetworks.ie and lets a homeowner submit it, but it recommends the installer completes it because of the technical questions on the inverter and protection settings. On every Solar Ireland install we file it for you.
The NC6 registers the system against the property's MPRN, so the registration stays with the home. The new owner takes on the system and would arrange their own export tariff with their supplier.
Written by
Cal Chesters
Founder & Lead Installer, Solar Ireland
Over 10 years in the Irish solar industry. Cal started Solar Ireland to cut through the noise and give homeowners a straight answer on what solar is worth.
More about Solar IrelandEverything above is general. Thirty seconds with your electricity bill turns it into your system size, your saving and your payback.
Related to: The NC6 Form Explained: Connecting Solar to the Grid